How Ratings Work

Each ordinance is rated in two ways. The Core Protections count shows how many of ten key protections the ordinance includes, and the Category Scorecard shows how thoroughly it covers each of eight topics.

Core Protections

These ten protections address the concerns residents raise most often in public polling and at Pennsylvania hearings. A protection is Partial when the ordinance sets a specific standard for it, and it is Full when that standard matches the strictest requirement shared by at least two adopted Pennsylvania ordinances.

  1. 1.Grid Cost Protection. Requires the data center, not other ratepayers, to cover the cost of new power lines and grid upgrades.
  2. 2.Water Supply. Requires proof that wells and water supplies will not be harmed.
  3. 3.Cooling Method. Requires water-saving cooling, such as closed-loop systems.
  4. 4.Generator and Air Limits. Limits backup diesel generator testing and air emissions.
  5. 5.Noise Limit. Caps how loud a data center can be at the property line.
  6. 6.Low-Frequency Noise. Addresses the low hum from cooling fans and equipment.
  7. 7.Public Transparency. Requires the developer and end user to be named and limits non-disclosure agreements with officials.
  8. 8.Farmland Protection. Keeps data centers off prime farmland or agricultural districts.
  9. 9.Home Setback. Requires a set distance between a data center and nearby homes.
  10. 10.Decommissioning Bond. Requires money set aside to remove the facility if it closes.
FullPartialNone

Electricity rates are set mainly by the Pennsylvania Public Utility Commission, so a zoning ordinance can only partly protect residents from higher bills. Generator and Air Limits is Partial or Full when the ordinance limits generator testing or air emissions, and Public Transparency is Partial or Full when it requires applicant disclosure or limits non-disclosure agreements.

Category Scorecard

All 52 criteria are grouped into eight categories: Land Use, Noise, Environment, Energy, Visual Character, Safety, Traffic, and Accountability. Each criterion is worth up to 2 points, and each category receives one of four levels.

StrongThe ordinance earns at least two-thirds of the category’s points.
ModerateThe ordinance earns between one-third and two-thirds of the points.
WeakThe ordinance earns some points, but less than one-third.
Not AddressedThe ordinance does not address the category at all.

Public Access

Every entry also records whether residents can read the ordinance. Public Access is reported separately and does not change the Core Protections count.

OnlineThe current ordinance and every amendment, including drafts under review, are posted as searchable text.
PartialThe ordinance is posted, but it is out of date, missing amendments or drafts, or posted only as a scan.
On RequestThe ordinance is not posted and must be requested from the municipal office.

Review Process

An ordinance is rated only from its full text, and David Olson, who maintains the tracker, reviews the ratings. Where the text could not be read, the entry shows Rating Pending. Proposed amendments are rated from the posted draft and are labeled as drafts. A municipality whose zoning has no data center provision is rated None, with 0 of 10 Core Protections.

See All 52 Criteria Below →

Tracker Standard: All 52 Criteria

Each criterion earns 2 points, 1 point, or 0 points, for a total of 104. An ordinance that falls short of the 1-point standard earns 0 points for that criterion.

  • Ratings come only from the full ordinance text: the zoning ordinance, its amendments, and any other adopted ordinance that applies to data centers.
  • An ordinance that meets only part of a multi-part 2-point standard earns 1 point.
  • A general rule that applies to all uses earns points only if the ordinance says it applies to data centers.
  • Criteria 51 and 52 may be met by any adopted ordinance, resolution, or policy.
Land UseCriteria 1 to 11
#Criterion2 Points1 Point
1District LimitsAllowed only in a dedicated data center overlay district.Limited to one or more named districts.
2Approval ProcessConditional use with a hearing before the governing body, and approval expires if construction does not begin within 1 year.Special exception by the Zoning Hearing Board.
3Agricultural LandBarred on preserved farmland and in agricultural security areas.Barred in agricultural districts only.
4Minimum Lot Size30 acres or more.Any smaller minimum.
5Maximum ScaleCap on building footprint or megawatts.Cap on lot coverage only.
6Residential Setback1,000 ft or more from residential uses or districts.100 to 999 ft.
7Sensitive-Use SetbacksAt least 1,000 ft from schools, day care centers, hospitals, and parks.A smaller distance, or only some of these uses protected.
8Height40 ft or less, and rooftop equipment no more than 10 ft above the roof.Any other height limit.
9Natural ResourcesRiparian buffer of at least 100 ft on each side of streams, wider on steep slopes and at wetlands.Environmental impact assessment required, or base ordinance protections stated as applying.
10Data Center SeparationMinimum distance between data center campuses.A campus of several buildings defined and regulated as one use.
11Expansion LimitsNew phases or added capacity require a new approval.Phasing plan required.
NoiseCriteria 12 to 17
#Criterion2 Points1 Point
12Noise LimitsSeparate day and night limits of 50 dBA and 45 dBA or lower at the property line.A single limit or higher limits.
13Background CapNo more than 10 dBA above existing background.Background cap above 10 dBA.
14Low-Frequency NoiseNumeric limits of 60 dBC day and 55 dBC night or lower.Higher dBC limit, or a low-frequency noise study required.
15Sound StudiesStudies with the application, at building permit, and after opening.Studies before construction, with or without a later study.
16Generator UseTesting limited to weekday daytime hours with a daily or annual hours cap.Daytime-only testing or an hours cap.
17VibrationNone perceptible past the property line, with a vibration study.A general vibration standard.
EnvironmentCriteria 18 to 25
#Criterion2 Points1 Point
18Water SupplyWells may not be used for cooling where public water is available, and any well use requires a hydrogeologic study with pump tests.Water feasibility study required.
19Cooling MethodClosed-loop required and evaporative cooling restricted.Cooling method must be disclosed.
20Water UseDaily cap or ongoing usage reporting, together with a drought response plan.One of these, or projected use disclosed.
21WastewaterPlan for cooling discharge approved before construction.General wastewater plan.
22StormwaterStormwater standards beyond the base ordinance.Base ordinance standards stated as applying.
23Air EmissionsGenerators must meet EPA Tier 4, with annual emissions testing or reports.Generators must meet state and federal emission rules.
24Waste HeatThermal impact plan including review of waste heat reuse.Heat impacts must be disclosed.
25Electronic WastePlan for removing and recycling servers, batteries, and refrigerants.General disposal requirement.
EnergyCriteria 26 to 31
#Criterion2 Points1 Point
26Power CapacityUtility confirmation of capacity before approval, and third-party electrical inspection before occupancy.Utility letter required before a building permit.
27Energy PlanEnergy usage plan plus required on-site renewable generation such as rooftop solar.Energy usage plan required.
28On-Site Power PlantsOn-site generation treated as a separate use with its own approval and setbacks.On-site generation addressed.
29Substations And LinesSubstations screened and placed to the side or rear, and on-site lines of 34.5 kV or less buried.Substations screened or counted as part of the use.
30Battery StorageNFPA 855 with battery-specific fire suppression.NFPA 855 or general fire code rules.
31Grid CostApplicant pays for grid upgrades the project requires.Required upgrades must be disclosed.
Visual CharacterCriteria 32 to 36
#Criterion2 Points1 Point
32BuffersPlanted buffer of 100 ft or more next to homes.Smaller buffer.
33LightingFully shielded, with no light crossing the property line.Shielded, with or without a footcandle limit.
34Building DesignSpecific facade or design standards.General design language.
35Fencing And ScreeningAll equipment screened on all sides, to at least 12 ft for ground equipment, with acoustic screening.Equipment must be screened.
36ViewshedVisual impact study from public roads and historic sites, with renderings.Building elevations required.
SafetyCriteria 37 to 40
#Criterion2 Points1 Point
37Emergency PlanPlan reviewed by the fire company, with annual updates, in-building radio coverage, and posted 24-hour contacts.Emergency plan required.
38First RespondersApplicant must fund first-responder training or equipment.Applicant must coordinate training.
39Hazardous MaterialsStorage setbacks and spill containment.Hazardous materials must be disclosed.
40InspectionsAnnual fire safety inspections and a third-party electrical inspection before occupancy.Annual inspections or an inspection at opening.
TrafficCriteria 41 to 43
#Criterion2 Points1 Point
41TrafficTraffic impact study in every case.Study above a size threshold.
42Road AccessArterial or collector road access and a secondary emergency access.One of these.
43Construction ImpactsWork hours, haul routes, and a road damage bond all set.Some of these.
AccountabilityCriteria 44 to 52
#Criterion2 Points1 Point
44DecommissioningSecurity of 110% of removal cost, notice of closure, removal completed within 6 months of abandonment.Agreement or plan without financial security.
45Cost UpdatesEstimate updated after the first year and at least every 5 years.Updated at least every 10 years or at transfer of ownership.
46Definition ScopeDefinition covers cryptocurrency mining and artificial intelligence or high-intensity computing.One of these.
47Compliance ReportingOngoing reports on noise, water, or power use.One report after opening.
48EnforcementSpecific penalties or permit revocation for violations.General enforcement provision.
49Independent ReviewApplicant pays for the municipality's own experts to review its studies.Independent review allowed, cost not assigned.
50Public EngagementApplicant community meeting before planning commission review and a project website kept current through final approval.One of these, or an extended comment period.
51Confidentiality AgreementsOfficials and staff barred from signing NDAs with data center applicants.NDAs allowed but must be disclosed and approved at a public meeting.
52Applicant DisclosureApplicant must name developer, operator, and end user before approval.Applicant must name developer or operator.

Overall bands by share of the 104 points: Comprehensive (80 to 100 percent), Substantial (60 to 79 percent), Moderate (40 to 59 percent), Limited (20 to 39 percent), and Minimal (1 to 19 percent).